Business and RFPs

Current Requests for Proposals


ADVERTISEMENT FOR BIDS

City of Burlington, Vermont Airport Improvement Program
Burlington International Airport, South Burlington, Vermont

AIP No. 3-50-0005-100-2014

Sealed Bids for Rehabilitate Terminal Apron, Phase 1 – Gates 13 and 13A at the Burlington International Airport, South Burlington, Vermont will be received by the Owner at 1200 Airport Drive #1, South Burlington, Vermont 05403 until 1:00 PM, Thursday, April 24, 2014 local time and then at said office publicly opened and read aloud.

This project includes Removal of existing portland cement concrete pavement, bituminous concrete pavement, drainage infrastructure; Installation of new drainage structures, pipes and trench drain; Placement of new crushed aggregate base course, stabilized bituminous base course, portland cement concrete pavement and bituminous concrete pavement; Placement of joint sealer and painted markings. Work will be located adjacent to Taxiway A and the Terminal Building at Gates 13 and 13A.

Contract documents may be examined on or after Wednesday, April 9, 2014 at:

1. Burlington International Airport, 1200 Airport Drive #1, South Burlington, Vermont 05403

2. Hoyle, Tanner & Associates, Inc., 150 Dow Street, Manchester, NH   03101

Copies may be obtained on or after Wednesday, April 9, 2014 at Hoyle, Tanner & Associates, Inc., 150 Dow Street, Manchester, NH 03101, Phone: Donna Akerley 603-669-5555, ext. 185, upon receipt of a non-refundable payment of $50.00 for each set. Make checks payable to “Hoyle, Tanner & Associates, Inc.”. 

To order a bid document by mail, please send a request to Hoyle, Tanner & Associates, Inc., 150 Dow Street, Manchester, NH 03101, and include a $20.00 non-refundable shipping and handling charge in addition to the $50.00 purchase price for the bid documents.

A MANDATORY pre-bid conference will be held at 10:00 AM, Wednesday, April 16, 2014 at the Burlington International Airport, 1200 Airport Drive #1, South Burlington, Vermont 05403.  This will be the only time for prospective Bidders or subcontractors to view the site.

The Owner reserves the right to waive any informality in the bidding or to reject any or all bids.

Each bidder must deposit with their bid, security in the amount of 5% of the bid in the form and subject to the conditions provided in the General Provisions.

Attention of bidders is particularly called to the requirements as to conditions of employment to be observed and minimum wage rates to be paid under the Contract.  The Contractor on this work will be required to comply with the equal employment opportunity requirements of the Federal Aviation Administration and the Burlington International Airport Disadvantaged Business Enterprise Program.

No bidder may withdraw his/her bid prior to September 30, 2014.